1, the installation generator suppliersite should be well ventilated, generator end should have enough inlet, diesel engine side should have a good outlet. Outlet area should be greater than the water area of 1.5 times.

Around 2, installation should be kept clean, avoid place nearby can produce acid, alkali and other corrosive gas and steam. Conditional should configure extinguishing equipment.

3, in indoor use, must be exhaust pipe through guide, outdoor pipe diameter must be out of the pipe diameter of silencer, pick up the line of the elbow should not be more than three, to ensure smooth smoke and pipe should be down 5-10 degrees, avoid rain water injection; If the exhaust pipe when the vertical installation, it must be equipped with cover.

4, when using the concrete foundation, must be used when the installation level measuring its levelness, make fixed in level on the basis of the unit. Between units and base should have special cushion or use the foot bolt.

Unit 5, the shell must be reliable grounding protection and the need to have a neutral point grounding of the generator directly, is a professional must to neutral grounding and lightning protection device configuration, it is forbidden to use mains grounding device of neutral point grounding directly.

6, generator and mains two-way switch must be very reliable, to prevent transmission. Two-way switch wiring reliability need to be approved by the local power supply departments of inspection.