Generator which checks should be obtained before starting
Update:2017-02-27 Tags:installation

Generator new installation or after major repair, dealing with before starting the generator to do the following check:

1) check the generator body parts installation is finished, is complete.

2) check whether the exciter commutator and generator slip ring surface is clean, brush whether complete, the brush spring pressure is even, should be no jamming phenomenon (without exciter who don't have to check on this).

3) check whether the installation is complete, the cooler air duct is tight, cooler air shall be free of. Check cooling system all sorts of auxiliary installation is complete.

4) check the control and signal device is installed, and security system and the experiments are in good condition.